Characteristics/Advantages

Tough Coat offers excellent crack-bridging properties and forms an elastomeric membrane that cures aerial moisture to a flexible, rubbery coating. It is a single-component, ready-to-use product that makes application easy by brush, airless spray, or roller. The coating is economical, abrasionresistant, hydrolysis-resistant, and root-resistant as part of a built-up system. It is resistant to mild acids, chemicals, industrial environments, and UV exposure. Additionally, it is low in VOCs and eco-friendly.

Application

Apply a primer coat of Tough Coat diluted with 50% clean water, which will cure in 2-4 hours depending on atmospheric conditions, with an approximate consumption of ~0.25 kg/m² using a hard brush, roller, or airless spray. Apply the first Coat of approximately 0.50 kg/m² of Tough Coat, then apply Non-woven Geotextile fabric / Pro Membrane on the surface and ensure no bubbles or creases. Overlap adjacent Non-woven Geotextile fabric / Pro Membrane by a minimum of 50 mm and allow this Coat to dry for at least 24 hours, depending on atmospheric conditions. Apply a second coat of approximately 0.50 kg/m² to achieve the required film thickness. Avoid spoiling the dry surface while walking on it while applying the material. The material should be applied within the workable time. Full curing may take up to 7 days, depending on temperature and humidity.

Product Information

#CharacteristicValue
1Chemical BaseAliphatic polyurethane-modified bituminous emulsion
2ColourWhite or other RAL colour
3Shelf Life12 months from the date of production
4Storage ConditionsStore in original, unopened, and undamaged sealed packaging in dry conditions at temperatures between +5℃ and +30℃
5Density1.20±0.05 kg/litre
6Solid Content by Weight≥ 60%
7Tensile Strength≥ 3.0 N/mm² (After 14 days at +27℃ with CLI pro membrane)
8Elongation> 250%
9Dew PointBeware of condensation! The substrate and uncured membrane must be at least 3°C above the dew point to reduce the risk of condensation
10Pot LifeApproximately 3 hours at 30℃
11Waiting Time / OvercoatingPrimer to Base Coat: 2-4 hours
First Tough Coat to Pro Membrane 1: Immediately in wet Base Coat
Second Tough Coat on Base Coat: 24 hours
Top Coat to Protection Screed: 7-10 days
12Drying TimeThe full cure requires about seven days at 30℃



Technical Data Sheet